He Ara Kotahi and Manawatū River cycle pedestrian pathway update

Council

25 February 2019

  1. That the approved budget for Capital New Programme 57 – He Ara Kotahi – Downstream Pedestrian/Cycle Bridge Construction be increased in total by $2,458,000 from $10,934,100 to $13,392,100, with Council’s share of the increase in budget not to exceed $1,030,000.
  2. That the approved programme budget for Capital New Programme 977 – Manawatu River (Fitzherbert Bridge to Linton) Cycle Pedestrian Pathway be increased in total by $1,767,000 from $3,702,100 to $5,469,100, with Council’s share of the increase in budget not to exceed $666,000.
  3. That the Chief Executive be instructed to continue to investigate options for increased third party funding and allocation of savings from 2018/19 Capital New Programmes to reduce the Council’s share of the cost to complete Programmes 57 and 977.
  4. That Council pursue lighting the link to Massey.