Programme 674: Church/Ruahine roundabout revised budget

Finance and Performance Committee

21 August 2017

  1. That Council approve a budget increase of $200,000 for programme 674 Church/Ruahine roundabout safety improvements, taking the total project budget to $575,000 for delivery in the 2017/18 financial year.
  2. That Council approve award of the construction tender for contract 3466 to Higgins Contractors for the contracted price of $520,206.
  3. That the Chief Executive be instructed to review all roading capital spend to assess any increases in cost that may impact the 2017/18 financial year.